Go on!Hengli Plans another $2.5 Billion Expansion as Shipbuilding Orders Extend to 2031

cover
Yang Chen(陈洋)
Published 12:13

Chinese shipbuilder Hengli Heavy Industries plans to invest a further RMB17 billion (approximately US$2.53 billion) in manufacturing facilities on Changxing Island in Dalian, as its delivery schedule extends to 2031. The proposal comes alongside a four-phase development programme, with the first two phases fully operating and the initial workshops in the third and fourth phases already in use.

The board of Shanghai-listed Guangdong Songfa Ceramics, Hengli's listed parent, approved the investment proposal on 27 November 2026. Hengli Shipbuilding (Dalian) Co., Ltd. would implement the project, which is intended to expand fabrication and supporting capacity for large, higher-value ships. Shareholder approval remains outstanding.

Four phases of development

Hengli's expansion began with the acquisition and rehabilitation of the former STX Dalian assets in 2022. Its first-phase "Ocean Factory" entered full operation in January 2023. Construction of the second-phase "Future Factory" started in August 2024, with production beginning in January 2025 after approximately five months of building work. The successive developments restored existing facilities and added modern manufacturing workshops for ships and key equipment.

The business also broadened beyond conventional ship assembly. On 14 September 2025, Hengli broke ground on two further industrial parks on Changxing Island, focused on collaborative innovation and offshore engineering technology. Their planned activities included marine composite materials, crankshafts, transmission equipment and navigation systems, alongside offshore platforms, floating production, storage and offloading vessels, and floating LNG facilities. A November 2026 report quoting Hengli Group chairman Chen Jianhua said the first workshops in the third-phase "Innovation Factory" and fourth-phase "Revitalisation Factory" had entered use.

In early 2026, Songfa outlined three projects with combined planned investment of approximately RMB13.509 billion (US$2.01 billion). These cover integrated green ship manufacturing, curved-block production upgrades, and supporting outfitting quays numbered 3 to 6. A 2 June research report by Soochow Securities classified this investment package as expansion of Hengli's third-phase factory.

Songfa subsequently completed a share placement raising approximately RMB7 billion (US$1.04 billion) in July, with net proceeds of about RMB6.941 billion (US$1.03 billion) to support those projects. The investment budget and the equity proceeds describe the construction programme and one of its funding sources. The proposal, financing approval and receipt of funds were successive steps in implementing the same package.

The relationship between the newly announced RMB17 billion project and the existing third- and fourth-phase developments remains to be clarified in further disclosures. The established picture is of several facilities moving through construction, commissioning and production ramp-up at the same time.

More fabrication and outfitting capacity

According to Songfa's filing dated 28 November, the proposed project would occupy approximately 10.53 million square metres, or 10.53 square kilometres, in the Dalian Changxing Island port area. Construction is scheduled to start in December 2026 and take 24 months. Of the RMB17 billion total budget, approximately RMB16.5 billion (US$2.46 billion) is designated as construction investment.

The facilities listed include steel storage areas, combined hull fabrication workshops, flat- and curved-block production shops, coating workshops, pre-outfitting facilities and superstructure workshops. Songfa says the project would complement existing production lines, relieve bottlenecks and strengthen construction and delivery capabilities, particularly for clean-fuel vessels and higher-value ship types.

Details of additional dry docks, simultaneous building positions and annual shipbuilding capacity attributable to this particular project await further disclosure. Its eventual contribution to output will depend on the facilities installed, the construction schedule and the pace at which production ramps up.

Hundreds of ships create a multi-year workload

Hengli's orderbook provides the immediate commercial backdrop. According to shipbroker Banchero Costa, the yard secured orders for 276 vessels during the first nine months of 2026 and held 485 outstanding orders at the end of September. Across the seven major merchant shipping segments covered by the broker, Hengli accounted for 23.4% of new contracting and 11.2% of the outstanding orderbook by compensated gross tonnage. On that basis, it ranked first among individual shipyards in both categories.

At the third Hengli Green Shipping Development Conference in October, Wang Lei, deputy general manager of Hengli Shipbuilding, put cumulative orders at more than 600 vessels. By late November, Liaoning Daily reported that the delivery schedule extended to 2031. Those contracts provide work for new facilities while requiring the existing organisation to handle a growing number of projects across design, procurement, construction and delivery.

Large dual-fuel containerships are a substantial part of that workload. Xinde Marine News reported on 23 October that Hengli had announced construction agreements covering 52 LNG dual-fuel vessels, comprising 20 of 19,000 TEU, 12 of 22,000 TEU and 20 of 24,000 TEU. Their combined nominal capacity is 1.124 million TEU, with Hengli planning to supply the main engines and LNG fuel tanks.

Such series orders create sustained demand for fabrication, machinery and specialist labour. Larger hulls and dual-fuel installations also require close coordination between structural work, equipment production and system installation. The ability to keep those activities aligned with contractual delivery dates will shape the execution of the orderbook.

Maersk's latest investment illustrates how major liner operators are planning vessel deliveries into the next decade. The carrier has confirmed orders for 12 dual-fuel containerships of 24,000 TEU for delivery in 2030 and 2031. The builder awaits disclosure by Maersk, while shipbroking reports have linked the order to Hengli.

Faster dock cycles depend on work ashore

In earlier regulatory responses, Songfa explained how block fabrication and dedicated assembly areas can move some work ahead of the dock stage. Completing more tasks before erection can shorten the period a vessel occupies a dock or building berth. Workshop layout, material handling and digital production planning also influence whether blocks reach the next operation on schedule.

This gives the proposed flat-block, curved-block, coating and pre-outfitting facilities a direct role in increasing output. When several ships are built simultaneously, shoreside workshops must supply their blocks at a matching pace. Delays in one type of block, component or installation preparation can affect the sequence of later work. Additional facilities consequently need to be accompanied by effective coordination across production stages.

Recent milestones show the scale of Hengli's parallel construction activity. Two 21,000-TEU LNG dual-fuel containerships left No. 3 dock on 16 October. Two more vessels of the same type left No. 2 dock on 17 November and moved into quayside outfitting. Four large containerships were thus launched within roughly a month, with outfitting, commissioning and sea trials still to follow before delivery.

The two MSC vessels launched in October were fitted with Hengli-built 8G95 LNG dual-fuel engines and 13,000-cubic-metre Type C fuel tanks. Manufacturing these components within the same industrial organisation allows the yard to coordinate equipment delivery dates, installation schedules and technical interfaces. The October development conference also reported planned engine production capacity of 300 units annually once the engine business reaches full output.

Series construction offers opportunities to apply lessons from earlier ships to subsequent vessels and repeat equipment orders. It also broadens the management task, as hull construction, engine production and fuel-tank manufacturing each require appropriate staffing, quality controls and investment.

Existing projects underpin the 2027 delivery target

Wang Lei said at the October conference that the yard planned to deliver 90 ships in 2026 and 120 in 2027. The latter target is approximately one-third higher, requiring dock turnover, quayside outfitting, commissioning and trials to support a larger annual output.

Earlier expansion projects are central to that increase. A previous regulatory response stated that, following implementation of the relevant investment projects, Hengli would have construction positions for 10 vessels below 200,000 dwt and 12 above that size, giving 22 simultaneous building positions. Supporting workshops and quays would help sustain continuous construction of large tankers and containerships.

The new RMB17 billion project operates on a longer timetable. A December 2026 start and 24-month construction period would put completion of construction around late 2028, followed by commissioning and production ramp-up. That schedule indicates that the 2027 delivery target will depend primarily on existing facilities and earlier expansion projects, while the newly proposed investment would progressively support later production.

Hengli must therefore maintain work on contracted vessels while installing equipment, commissioning production lines and staffing new facilities. Each development phase needs to connect with the construction milestones of ships already in the programme.

Profits rise alongside capital spending

For the first nine months of 2026, Songfa reported revenue of RMB37.774 billion (US$5.63 billion) and net profit attributable to shareholders of RMB6.673 billion (approximately US$995 million). These represented year-on-year increases of 221.25% and 424.87%, respectively, using the report's retrospectively adjusted comparative figures. Songfa attributed the growth mainly to its larger business scale and increased numbers of vessels under construction and delivered.

Operating activities generated net cash of RMB13.496 billion (US$2.01 billion) over the nine-month period, while cash paid to acquire and construct fixed assets, intangible assets and other long-term assets reached RMB22.380 billion (US$3.34 billion). Operating receipts, equity funding and bank financing have together supported the expansion of the business and its asset base.

For the new project, Songfa plans to use internal resources, bank loans and other financing, with expenditure phased according to construction progress. The company says development will create substantial construction-in-progress and fixed assets, followed by higher depreciation and amortisation after commissioning. It also acknowledges some near-term pressure on cash flow.

Utilisation will influence the return on that investment. In previous regulatory disclosures, Songfa explained that dock and berth depreciation and major equipment maintenance costs are relatively fixed. Building more ships simultaneously can reduce the manufacturing overhead allocated to each vessel. Maintaining continuous production and improving facility turnover will therefore need to progress alongside construction cost control and financing arrangements.

The RMB17 billion proposal remains at the preparatory stage and is scheduled for shareholder consideration on 15 December. Project filing, environmental assessment, planning and construction permissions are among the procedures involved. Its detailed implementation timetable and integration with Hengli's existing development phases should become clearer as the project advances.static.cninfo.com.cn

US-dollar equivalents use the China Foreign Exchange Trade System central parity rate of RMB6.7075 per US$1 on 27 November 2026. Figures are rounded.